H.Peshk

Koka & Ergi Energy Stavec is registered in the National Registration Center (QKR) date 27.06.2008 with identification number (NUIS) K88027902J, represented by its legal administrator Mr. Mehmet Koka.

HPP “Stavec” is expected to be built in northern Albania in the south of the village Krasta, between the villages Blisht and Plan Bardhe. The purpose of its construction is the production of electricity by using the waters Mat’s river between quota 437 m and 350 m by a derivation in a length of about 4.43 km which traces on the left bank of the river.


Main indicators:

Koka & Ergi Energy Stavec
TypeWith Derivation
Water level on the top side437 m
Water level on the above side350 m
Renja Bruto87 m
Renja Neto80.4 m
Prurja Llogaritese9.5 m3/s
Fuqia e Instaluar6.8 Mw
Energjia mesatare vjetore, E33.12 Gwh
Energjia e prodhuar ne vitin e thate29.02 Gwh
Energjia e prodhuar ne vitin e laget36.95 Gwh
Ore pune ne vitin Mesatar5084 Ore
Ore pune ne vitin e Thate4454 Ore
Ore pune ne vitin e Laget5670 Ore
Turbina tipi Frencis me Aks Horizontal2 cope
Fuqia e turbines3.26 Mw
Tubacione turbinash me diameter D=2100mm1 cope

Water is taken in the village Blisht at the point where is expanded the gorge (several meters above the existing pedestrian bridge). The powerhouse is expected to be built on the left bank about 100 m below the point where streams the torrent of Plan Bardhe in Mat’s river.

HPP “Stavec” is under construction. Total estimated investment amount is approximately 8,000,000 euro.